Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
Report of the Head of Development Management and Building Control
Committee Report
Case Officer: Alan Corcoran 829/APP/2023/312
Date Application
Valid:
19.05.2023 Statutory / Agreed
Determination
Deadline:
14.09.2025
Application
Type:
Full Ward: Heathrow
Villages
Applicant: Phull Empire Ltd
Site Address: 560 Sipson Road, West Drayton, UB7 0JD
Proposal: Redevelopment of the site to accommodate a 7-
storey 108
-room hotel incorporating communal
functions on the ground floor level and a
basement level with associated parking and
external landscaping works including coach
parking, servicing areas, and planting.
Summary of
Recommendation:
GRANT planning permission subject to section
106 legal agreement and conditions
Reason Reported
to Committee:
Required under Part 1 of the Planning Scheme of
Delegation (Major application recommended for
approval)
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
Summary of Recommendation:
GRANT planning permission subject to the completion of a satisfactory
section 106 legal agreement to secure the heads of terms set out below, and
subject to the conditions as set out in Appendix 1.
It is recommended that delegated powers be given to the Director of Planning
and Sustainable Growth to grant planning permission subject to the following:
A) That the Council enter into a legal agreement with the applicant under
Section 106 of the Town and Country Planning Act 1990 (as amended) or any
other legislation to secure the following:
i. Air Quality Mitigation contribution of £974,383.
ii. A Carbon Offset sum based on an Updated Energy Strategy to discharge
Condition 22, with the offset calculation based on £95 per tonne of CO2 over a 30-
year period.
iii. A Construction Employment Training Scheme secured in accordance with the
Council's Planning Obligations SPD.
iv. An End-User Employment Scheme secured in accordance with the Council's
Planning Obligations SPD.
v. A Section 278 agreement to implement the proposed off-site Highways Works
and street tree planting on Sipson Road.
vi. A Project Management and Monitoring Fee, equalling 5% of the total financial
contributions to be paid under this agreement.
B) That in respect of the application for planning permission, the applicant
meets the Council's reasonable costs in preparing the Section 106 Agreement
and any abortive work as a result of the agreement not being completed.
C) That officers be authorised to negotiate and agree the detailed terms of the
proposed agreement and conditions of approval.
D) That, if the Legal Agreement has not been finalised within 6 months (or
such other time frame as may be agreed by the Director of Planning and
Sustainable Growth ), delegated authority be given to the Director of Planning
and Sustainable Growth to refuse planning permission for the following
reason:
'The applicant has failed to mitigate the impacts posed by the proposed
development (in respect of A ir Quality, Carbon Emissions, Employment and
Highways works). The scheme therefore conflicts with Policies DMCI 7 of the
Hillingdon Local Plan: Part 2 ( 2020); the adopted Planning Obligations
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
Supplementary Planning Document (2014); Policy DF1 of the London Plan
(2021); and paragraphs 56 -58 of the National Planning Policy Framework
(2024).'
E) That if the application is approved, that the permission is subject to the
Conditions as set out in Appendix 1.
1 Executive Summary
1.1 The vacant 0.27-hectare application site is located to the north of Heathrow Airport
on the western side of Sipson Road. The Site is within Potentially Contaminated
Land, an Air Quality Management Area (AQMA), an Air Quality Focus Area
(Sipson Focus Area), and an Archaeological Priority Zone (Heathrow). It is within
Flood Zone 1 - the lowest probability of flooding, and Surface Water Flooding does
not affect the Site. It is, however, within a Critical Drainage Area. The Site is not
Listed or located within a Conservation Area or Area of Special Local Character.
1.2 The Council previously granted planning permission in 2018 (application reference
829/APP/2016/3167) for a seven-storey 108-room hotel on this Site. This consent
has not been implemented. The current proposal consists of the redevelopment of
the Site to accommodate a seven-storey 108-room hotel incorporating communal
functions on the ground floor level and a basement level with associated parking
and external landscaping works, including coach parking, servicing areas, and
planting.
1.3 Given the Site’s planning history (planning consent to construct a hotel in 2013
and 2018), and on review of the submitted Sequential Test, the principle of
developing a hotel on this site is acceptable. The building’s height, scale, and
mass are comparable to the surrounding context, and it would not impact
residential amenity. There are no objections from the Council’s Urban Design
Officer, Landscape Officer, or Highways Officers. While located on Potentially
Contaminated Land, the Council’s Land Contamination Officer has no concerns
subject to the recommended condition. Noting the Air Quality Management Area
(AQMA) and Air Quality Focus Area, which the Site is within, the Council’s Air
Quality Officer has no objections subject to an air quality mitigation contribution of
£974,383 (contained within the Section 106 Heads of Terms) and planning
conditions, which have been recommended. Whilst the Site is within an
Archaeological Priority Zone (Heathrow), Historic England’s Greater London
Archaeological Advisory Service (GLAAS) has no objection subject to the attached
conditions.
1.4 The Council received one objection from the Heathrow Villages Conservation Area
Advisory Panel, which raised concerns regarding soft landscaping. Additional soft
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
landscaping has been added, and a green roof. Street trees would be planted
through the Section 278 Agreement.
1.5 The proposal is acceptable and would be consistent with the relevant development
plan policies.
1.6 The planning application is therefore recommended for approval subject to the
conditions contained in Appendix 1 and Section 106 Heads of Terms detailed on
the previous page.
2 The Site and Locality
2.1 The 0.27-hectare application Site is located to the north of Heathrow Airport on
the western side of Sipson Road, a classified A road (A408). The Site is to the
east of the M4 motorway and north of the A4 (Bath Road), the latter forming the
northern boundary to Heathrow Airport. The Site is vacant and has been for
several years. It previously comprised a two -storey building used as a clubhouse
for the Royal British Legion.
2.2 The Site is within Potentially Contaminated Land, an Air Quality Management Area
(AQMA), an Air Quality Focus Area (Sipson Focus Area), and an Archaeological
Priority Zone (Heathrow). It is within Flood Zone 1 - the lowest probability of
flooding, and Surface Water Flooding does not affect the Site. It is, however, within
a Critical Drainage Area. The Site is not Listed or located within a Conservation
Area or Area of Special Local Character.
2.3 Existing vehicle access is off Sipson Road, with an expanse of hard surface that
previously accommodated the parking and servicing space for the clubhouse. The
Site has a Public Transport Accessibility Level (PTAL) of 3, on a scale of 0 to 6b,
where 6b is the highest.
2.4 The Site forms part of a larger 'island' block that transport infrastructure surrounds.
Within the 'island', there is a large hotel, with associated health & fitness and
restaurant facilities, and significant levels of surface car parking. These buildings
are generally between four and six storeys high. To the northeast of the Site and
Sipson Road is Sipson Farm, designated Green Belt land, which has consent for
sand and gravel extraction. To the east of the Site, located over 100 metres away,
on the opposite side of Sipson Road, is a children's nursery accommodated within
two buildings known as Sipson Court and Sipson House. Sipson House is Grade
II Listed. The nearest residential dwellings to the Site are located over 110 metres
to the south of the Site and on the opposite side of Sipson Road.
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
Figure 1: Location Plan (application site edged red)
Figure 2: Aerial View of the Application Site
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
Figure 3: Street View Images of the Application Property
View from Sipson Road
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
View from Sipson Road
3 Proposal
3.1 On 10.09.2018, the Council approved the following on this application site
(application reference 829/APP/2016/3167):
‘Redevelopment of the site to accommodate a 7 -storey 108 room hotel
incorporating breakfast area and working/living zone at ground floor level; a
basement level with associated parking; and external landscaping works including
provision of parking, servicing areas, and planting.’
3.2 The current application is broadly a resubmission of the previously approved
scheme (application reference 829/APP/2016/3167), which the developer did not
construct. This current application seeks planning permission to redevelop the site
to accommodate a seven-storey 108- room hotel incorporating communal
functions on the ground floor level and a basement level with associated parking
and external landscaping works, including coach parking, servicing areas, and
planting.
3.3 The hotel would measure approximately 31 metres wide at the front, narrowing to
15 metres at the rear. It would be approximately 29 metres deep and have a height
of 21 metres (seven storeys). It would have a gross internal floor area of 5,619 sq.
m.
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
3.4 Vehicle and pedestrian access to the development would continue from Sipson
Road. Two car lifts would be provided to allow cars to enter and exit the basement
car parking area. A total of 19 car parking spaces would be provided. Two of the
car parking spaces would be designated as disabled -person parking bays. Three
spaces would have active electric vehicle charging points. 16 cycle parking spaces
would be provided. Coaches and taxis would enter the forecourt at the front of the
Site to collect and drop off hotel guests.
Figure 4: Proposed Plan (please note – larger version of plan can be found in
the Committee Plan Pack)
Proposed Site Plan
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
Proposed Front Elevation
Proposed 3-D Visual from Sipson Road
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
Front Elevation of the Previoulsy Approved Hotel on the Site (application reference
829/APP/2016/3167) that the Developer did not Construct.
4 Relevant Planning History
4.1 A list of the relevant planning history related to the property can be found in
Appendix 2.
5 Planning Policy
5.1 A list of planning policies relevant to the consideration of the application can be
found in Appendix 3.
6 Consultations and Representations
6.1 The Council sent consultation letters to 31 neighbouring properties and the
Harmondsworth and Sipson Residents Association on 26-05-2023. The Council
also advertised the application with a site notice and press notice on 07 -06-2023.
The initial consultation expired on 28 -06-2023. The Council carried out a full
reconsultation on 18-10-2024. The reconsultation period expired on 07-11-2024.
6.2 The Council received one objection in response to public consultation from the
Heathrow Villages Conservation Area Advisory Panel, which raised concerns
regarding the proposed landscaping. Consultee responses received are
summarised in Table 2 (below). Full copies of the responses have also separately
been made available to Members.
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
Table 1: Summary of Representations Received
Representations Summary of Issues
Raised
Planning Officer
Response
The Council
received one
objection from the
Heathrow Villages
Conservation
Area Advisory
Panel.
Concerns regarding the
lack of soft landscaping
and green roof.
The Applicant submitted
revised landscape plans
and details regarding a
green roof to address
these concerns.
Table 2: Summary of Consultee Responses
Consultee and Summary of Comments
Planning Officer
Response
External Consultee Comments
Greater London Archaeological Advisory Service
(GLAAS):
No objection subject to condition and informative
regarding a Written Scheme of Investigation.
A condition and
informative have been
recommended in line
with GLAAS’
recommendations.
Transport for London (TfL):
No objection subject to condition s regarding Coach
Parking Management Plan, Delivery and Servicing
Management Plan and Construction Logistics Plan,
cycle parking, and electric vehicle charging provision.
Conditions have been
recommended in line
with the TfL’s
recommendations.
Metropolitan Police Design Out Crime:
No objection subject to a condition regarding ‘Secured
by Design’ accreditation.
A condition has been
recommended in line
with the Metropolitan
Police’s
recommendations.
National Air Traffic Services:
No objection.
Noted.
Heathrow Airport:
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
No objection. Informative recommended regarding
cranes.
An informative has
been recommended
in line with Heathrow
Airport’s
recommendation.
Thames Water Utilities:
No objection subject to a condition regarding a Piling
Method Statement and informative.
A condition has been
recommended in line
with the Thames
Water Utilities’
recommendations.
Internal Consultee Comments
Urban Design Officer:
No objection subject to a condition regarding external
materials.
A condition has been
recommended in line
with the Urban Design
Officer’s request.
Landscape Officer:
No objection subject to conditions regarding
landscaping.
Conditions have been
recommended in line
with the Landscape
Officer’s
recommendations.
Economic Development:
No objection subject to a Construction Employment
Training Scheme and an End -User Employment
Scheme being secured in accordance with the
Council's Planning Obligations SPD via a Section 106
Agreement.
This request is a
recommended Heads
of Terms to be
secured in the Section
106 Agreement.
Accessibility Officer:
No objection subject to conditions regarding the car
park lift, disabled person car parking provision, and
hotel room accessibility.
Conditions have been
recommended in line
with the Accessibility
Officer’s
recommendations.
Refuse and Recycling Officer:
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
No objection. Noted.
Planning Policy Officer:
No objection.
Noted.
Highways Officer:
No objection subject to conditions regarding car
parking lift maintenance, swept paths, Service and
Delivery Plan, Construction Logistics Plan, Travel
Plan, and a Section 278 Agreement to implement the
proposed off-site Highways Works.
Condition s have been
recommended in line
with the Highways
Officer’s
recommendations,
and a Section 278
clause is included in
the recommended
Heads of Terms.
Air Quality Officer:
No objection subject to an Air Quality Mitigation
contribution of £974,383 secured by a Section 106
Agreement and a condition regarding reducing
emissions from demolition and construction.
A Section 106
financial contribut ion
is included in the
recommended Heads
of Terms and a
condition has been
recommended in line
with the Air Quality
Officer’s
recommendations.
Noise Pollution Officer:
No objection.
Noted.
Environmental Health Officer (Land
Contamination):
No objection subject to a condition regarding land
contamination.
A condition has been
recommended in line
with the Land
Contamination
Officer’s
recommendations.
Environmental Specialist (Energy and
Biodiversity):
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
No objection subject to a condition requiring a revised
Energy Strategy and a carbon offset contribution
based on the updated Energy Strategy and ‘be seen’
energy monitoring condition.
A Section 106 carbon
offset contribution
obligation is proposed
in the recommended
Heads of Terms.
Conditions have been
recommended in line
with the
Environmental
Specialist (Energy
and Biodiversity).
Flood Risk and Drainage Consultant:
No objection subject to Detailed Drainage Design and
Sustainable Drainage Scheme planning conditions.
Conditions have been
recommended in line
with the Flood Risk
and Drainage
Consultant’s
recommendations.
7 Planning Assessment
Principle of Development
7.1 The application Site has been vacant for several years. The planning history is
relevant to the consideration of whether the principle of hotel use on this site is
deemed acceptable. However, it should be noted that there have been significant
policy changes since the approval of the most recent application
(829/APP/2016/3167) was determined in 2018.
7.2 More specifically the Hilli ngdon Local Plan Part Two was adopted in 2020 and
specific locations for which hotel development should be focused. These include
Town Centres and designated locations for hotel growth. Notably this site is not
located within an area designated for hotel growth or a Town Centre. As such for
the principle of development to be deemed acceptable the applicant must submit
a sequential test.
7.3 The Applicant submitted a Sequential Test (Sequential Assessment Scoping
Note, prepared by Turley and Sequential Assessment, reference G AAP3000,
prepared by Turley, dated November 2023) to demonstrate why it is an
appropriate hotel location, despite not being in a Town Centre or Hotel Growth
Location.
7.4 The Council's Planning Policy Team has been consulted and has reviewed the
submission documents. They do not raise any objection to this proposed hotel
development, advising that the Sequential Test provides evidence of the limited
availability of land for hotels in relevant Town Centres. When this is considered
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
against the strategic need for serviced visitor accommodation set out in The
London Plan (2021) and its associated evidence base, it is apparent that the need
for serviced visitor accommodation cannot be met on Town Centre and Edge-of-
Centre sites alone. A refusal of the application on this basis is therefore not
justified or recommended.
7.5 As such, the proposal complies with Policy E10 of The London Plan, Policy E2 of
the Hilli ngdon Local Plan Part 1, and Policy DME 5 of the Hillingdon Local Plan
Part 2.
Design / Impact on the Character and Appearance of the Area
7.6 The application site is a pocket of vacant land located north of the Raddison and
Park Inn hotels. Both neighbouring hotels benefit from much greater sized plots.
The Radisson is 4-6 stories in height and features 6 arms orientated off a central
horizontal spine. The Park Inn is a 5 storey L-shaped building constructed of red
brick and a cladded frame. This frame and the angled brickwork which helps
create the angled windows adds visual interest and articulation to a building which
features extensively wide façades. Both neighbouring hotels feature reasonably
large car parks but are set within a boundary of mature trees and planting which
softens the hard surfaced dominated areas to the front and rear of the buildings.
7.7 The proposed building is similar in all aspects of design and appearance
compared with the previously approved hotel development on the Site (application
reference 829/APP/2016/3167). The proposed seven
-storey building height would
reflect the local context and surrounding developments, particularly the adjacent
six-storey hotel. The proposed building's footprint and overall scale would be
smaller than the neighbouring hotel complex and would respect the area's
prevailing scale of development. The building's elevations would include vertical
protruding fins to appropriately articulate the facade and provide visual relief to
the building's elevations. Its appearance would be in keeping with the area's
character, and the proposed building would sit comfortably within the streetscene.
The double -height entrance with a canopy across the facade would ensure a
legible front elevation, and when combined with the upper floor setback would
ensure a visually appropriate appearance from the street
7.8 The Council’s Urban Design Officer has been consulted and has no objections
regarding the proposed design subject to a condition regarding materials which
has been recommended.
7.9 The proposal complies with Paragraph 131 of the NPPF, Policies D3 of The
London Plan, Policy BE1 of the Local Plan Part 1, and Policies DMHB 11 and
DMHB 12 of the Local Plan Part 2.
Residential Amenity
7.10 There are no homes within 100 metres of the Site and the nearest residential
dwellings are on the other side of Sipson Road. The pr oposal would not impact
the outlook, privacy, daylight, or sunlight of nearby homes or open spaces, given
its height, scale, mass, use, and location away from residential properties.
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
7.11 The closest neighbouring buildings are hotels. The proposed hotel would not
contain a large internal floor area allocated for conference or banqueting
purposes. As such, the proposal would not cause undue noise disturbance to
surrounding properties.
7.12 Please see relevant sections below regarding noise.
7.13 The proposed scheme is supported and complies with Policy D3 of The London
Plan (2021) and Policy DMHB 11 of the Local Plan Part 2 (2020).
Highways and Parking
7.14 Sipson Road is a two-way local distributor road that connects with Bath Road (A4)
to the south and Holloway Lane (A408) to the north. It has one carriageway in
either direction, a 30mph speed limit, double yellow line parking restrictions, and
a pedestrian footway on the southern side of the carriageway, together with a
grass verge and street lighting at regular intervals. The site is situated in a location
with a Public Transport Accessibility Level (PTAL) of 3, where a score of 0
indicates very poor access to public transport and 6 indicates excellent access.
7.15 The proposed development would have 19 on-site basement car parking spaces.
Two of these would be allocated for disabled person parking and three would be
fitted with active electric vehicle charge points (EVCPs). Access to the basement
parking would be provided by two car lifts and there would be capacity for two cars
to wait onsite in the hotel’s forecourt before entering the lifts to the basement.
There would be provision for coaches and taxis to enter the hotel forecourt to pick-
up/drop-off guests.
7.16 Policy T6.4 of The London Plan (2021) is non-prescriptive for hotel car parking. It
states that hotel car parking ' should be assessed on a case-by- case
basis'. Similarly, the Hilli ngdon Local Plan: Part 2 - Development Management
Policies (2020) is also non -prescriptive, stating that car parking numbers should
be determined on an ' individual basis'. Considering the good availability of long-
stay car parking in the vicinity of the Site, the Site's PTAL of 3, and the available
travel choices, the proposed 19 car parking spaces are appropriate and would not
lead to parking displacement or stress. Conditions are recommended to ensure
the delivery and ongoing availability of the disabled person parking and EVCPs.
7.17 Sixteen covered cycle parking spaces would also be provided within the hotel’s
forecourt. Two of these would be designated for larger adaptable bicycles. The
proposed cycle parking provision aligns with The London Plan and Local Plan
standards. Conditions are recommended to ensure their delivery and ongoing
availability.
7.18 To allow the new site accesses to be built the Highway Authority require that the
Applicant enter a Section 278 Agreement thereby allowing contractors to work on
the Council’s highway in collaboration with Council’s highway officers. As part of
these works, the footway and grass verge either side of these accesses shall be
reinstated. The Highway Authority require that the full length of the footway in
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
between each access is reinstated together along with the provision of street
trees.
7.19 The Council’s Highways Team has been consulted and raise no objection to the
proposed development subject to conditions regarding car parking lift
maintenance, swept paths, Service and Delivery Plan, Construction Logistics
Plan, Travel Plan, and a Section 278 Agreement to implement the proposed off-
site Highways Works. Appropriate highways conditions are recommended in this
planning assessment and recommendation, and a Section 278 clause is included
in the recommended Heads of Terms.
7.20 Subject to the recommended conditions and Section 278 Agreement, the proposal
complies with Paragraph 116 of the NPPF, Policies T2, T4, T5, T6, and T7 of The
London Plan, and Policies DMT 1, DMT 2, DMT 5, and DMT 6 of the Local Plan
Part 2.
Air Quality
7.21 The Site is within an Air Quality Management Area (AQMA) and an Air Quality
Focus Area (Sipson Focus Area).
7.22 The Applicant submitted an Air Quality Assessment (reference, AQ2114,
prepared by GEM Air Quality Ltd, dated July 2022).
7.23 The proposed development would not be air quality neutral or air quality positive.
Therefore, further appropriate mitigation is required.
7.24 Mitigation measures to reduce emissions can be applied on-site or off-site. Where
this is not practical or desirable, pollutant off- setting will be applied. The level of
mitigation required associated with the operation phase of the proposed
development is calculated using Defra’s Damage Cost Toolkit in this instance. Any
mitigation measures proposed will be evaluated in terms of likely emission
reductions onto local air quality. Wherever quantifiable, these are calculated and
subtracted from the overall value due. When no quantification is possible, a flat
rate discount is applied. Mitigation required to offset the proposed development's
traffic emissions is £974,383.
7.25 The Council’s Air Quality Officer has been consulted and raised no objection
subject to an air quality mitigation contribution of £974,383 secured by a Section
106 Agreement and a condition regarding reducing emissions from demolition and
construction. This Section 106 financial contribution is included in the
recommended Heads of Terms and a condition has been recommended in line
with the Air Quality Officer’s recommendations.
7.26 Subject to legal agreement and the recommended conditions, the proposal
complies with Policies SI 1 and GG3 of The London Plan, Policy EM8 of the Local
Plan Part 1, and Policy DMEI 14 of the Local Plan Part 2.
Noise
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
7.27 The Applicant submitted a Noise Impact Assessment (reference 23907.NIA.01,
prepared by KP Acoustics, dated 13.07.2022) assessing daytime and night- time
levels likely to be experienced by the proposed development. To mitigate internal
noise levels, the Applicant proposed a robust glazing specification . Their report
concludes that no further mitigation measures are required to protect the internal
spaces from external noise.
7.28 As previously stated, the nearest residential dwellings to the Site are located over
110 metres to the south of the Site and on the opposite side of Sipson Road.
Given the notable separation distance, the proposed development would not
cause undue noise disturbance to nearby residents.
7.29 The Council's Noise Pollution Officer has reviewed the submission and raised no
objection or concerns about noise and vibration g iven the nature and context of
the proposed development.
7.30 A Construction Management Plan condition is recommended to mitigate and
manage potential noise disturbances.
7.31 The proposal complies with Policies D13 and D14 of The London Plan.
Accessibility
7.32 The supporting Design and Access Statement (Rev-P01, prepared by GAA, dated
18.07.2023), and plans demonstrate inclusive access. Nine per cent of hotel
rooms are proposed to be fully accessible to wheelchair -using guests. A further
one per cent are proposed to have a fixed tracked -hoist system or a similar. All
en-suite bathrooms within the Univer sal Access guestrooms are designed to the
layout detailed in BS 8300 -1:2018, figure 30. 75 per cent of the en- suite
bathrooms within the accessible bedrooms are proposed to have level access
showering facilities. Lifts are proposed to comply with BS 8300:2018+A1:2010,
and a fire evacuation lift to BS EN 81-76 standard is proposed.
7.33 The proposal includes two disabled person car parking spaces and two adaptable
cycle parking spaces. This level of disabled person car and cycle parking is
supported.
7.34 The Council’s Accessibility Officer has reviewed the pr oposal and raised no
objection subject to conditions regarding the car park lift, disabled person car
parking provision, and hotel room accessibility. Appropriate accessibility planning
conditions are recommended as part of the planning assessment and planning
recommendation.
7.35 Subject to compliance with the recommended conditions, the proposed
development complies with Policies D5 and D12 of The London Plan.
Urban Greening, Landscaping, and Public Realm
7.36 The existing site suffers from an evident lack of greening. It consists of
hardstanding.
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
7.37 The Applicant submitted an Arboricultural Impact Assessment (reference
HWA10759-APIII, prepared by Ha llwood Associates, dated 20.06.2022), which
detailed trees on and close to the S ite, the tree species, and their quality and
spread. None of the trees are protected by a Tree Preservation Order or by
Conservation Area designations. The only on-site tree is a Sycamore that is of 'U'
grade and would be removed as part of the proposal. During the planning process,
the Council worked with the Applicant to secure revised landscaping, namely
additional planting. The front and sides of the Site are proposed to contain raised
planters with soft landscaping. The Applicant submitted revised plans that propose
a biodiverse green roof to cover 105 sq. m., which is secured by condition. The
Council’s Landscape Officer advised that ‘the updated proposals have satisfied
the Urban Green Factor by providing a green/brown roof.’ Additionally, trees would
be planted on Sipson Road in front of the Site. These are secured by the Section
278 Agreement. The proposed uplift in planting compared with the previous
approval and the existing Site is acceptable.
7.38 Policy DMEI 1 of the Local Plan Part 2 requires all major development to
incorporate living roofs and/or walls. The proposal includes a green roof.
7.39 Subject to conditions, the proposal would comply with the aims Policy G5 of The
London Plan and Policy DMHB 14 of the Local Plan Part 2.
Biodiversity
7.40 The Applicant submitted a Preliminary Ecological Appraisal (prepared by
Henriette Westergaard, dated 04.07.2022), which details that the existing Site
comprises developed land of negligible ecological importance.
7.41 As the application was submitted in 2023, it is not subject to recent Biodiversity
Net Gain requirements. Nonetheless, the proposal would see an uplift in
biodiversity on the Site as the current Site is entirely hardstanding at present, and
the proposed Site would contain soft landscaping and planting features at ground
level. Furthermore, there would be a 105 sq. m. biodiverse green roof (drawing
reference 10513-LA-01-Rev-P1) that would enhance the Site’s biodiversity.
7.42 The Council’s Environmental Specialist (Energy and Biodiversity) reviewed the
submitted biodiversity details and raised no objection regarding the proposed
development.
7.43 The proposed development complies with the aims of Policy 15 of the NPPF,
Policy G6 and Paragraph 8.6.6 of The London Plan, and Policy DMEI 7 and
Paragraph 6.28 of the Local Plan Part 2.
Flooding and Drainage
7.44 The Site is in Flood Zone 1 (lowest flood risk) and is not impacted by Surface
Water Flooding. It is , however, within a Critical Drainage Area. The existing Site
comprises hardstanding. As such, there are no natural forms of attenuation within
the Site boundary. It is fully impermeable.
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
7.45 The Applicant submitted a Drainage Strategy (Rev-P03, reference 18403-RLL-22-
XX-RP-C-001, prepared by RLRE Consulting Engineers, dated 30.06.2022). It
states that a s there are no watercourses in proximity of the Site, the developer
has chosen an outfall to the adjacent surface water sewer in accordance with the
hierarchy for SuDS to provide sufficient attenuation to ensure that there would be
no off-site flooding for return periods up to and including the one in 100 year plus
40 per cent climate change event. The Applicant proposes to attenuate flows
within a blue roof system (providing 45.7m3 storage), the permeable sub -base
(providing 27.3m3 total storage), and two below -ground tanks (providing 12m3
total storage) on the podium deck outside the building’s entrance. Additionally, the
Applicant proposes rainwater harvesting via a 12m3 storage tank in the basement.
Water treatment would generally be provided via the underdrained swale and
permeable sub-base on the podium slab.a private management company would
maintain the SuDS features.The Applicant proposes to pump foul flows from the
Site via a private pumping station within the basement. The pumped flows would
outfall to a break chamber within the Site boundary before draining via gravity to
the existing Thames Water foul sewer in Sipson Road.
7.46 The Council’s Flood Risk and Drainage Consultant has reviewed the submission
and raised no objection subject to Detailed Drainage Design condition and
Sustainable Drainage Scheme condition. Appropriate drainage conditions are
recommended as part of this planning recommendation.
7.47 Subject to the recommended conditions, the proposed development is acceptable
with regard to Flooding and Drainage and complies with Policies SI12 and SI13
of The London Plan, Policy EM6 of the Local Plan Part 1, and Policies DMEI 9
and DMEI 10 of the Local Plan Part 2.
Water Efficiency
7.48 To ensure the development would minimise the use of mains water, a compliance
planning condition is recommended for it to achieve at least the BREEAM
excellent standard for the ‘Wat 01’ water category or equivalent (commercial
development), and incorporate measures such as smart metering, water saving,
and recycling measures, including retrofitting.
7.49 Subject to the recommended condition, the proposal complies with Policy SI 5 of
The London Plan.
Energy and Sustainability
7.50 The Applicant has submitted an Energy Strategy Report (reference 20-8895,
prepared by Syntegra, dated 16.07.2022) and BREEAM Pre-Assessment Report
(Reference 21-8895, prepared by Syntegra, dated 03.08.2022).
7.51 That submission states that the hotel would achieve a Building Research
Establishment Environmental Assessment Method (BREEAM) Rating 'Excellent',
with a score of at least 71.15 percent based on the latest BREEAM NC Technical
guidance. Air Source Heat Pumps (ASHP) would be used to generate heating,
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
cooling, and hot water for the proposed development. To bring the development's
carbon savings up to 100 per cent, carbon emissions are to be offset through a
carbon offset payment. A carbon offset payment, priced at £95 per tonne of CO2
per year (over 30 years) is to be paid via a Section 106 to the Council following
review of a revised Energy Strategy, which is recommended by condition. Policy
DMEI 2 of the Hilli ngdon Local Plan requires all major developments to be
designed to connect to a District Energy Network and to connect to ones within
500 metres of the development. As there are no networks within 500 metres from
the proposed development, no plans are in place to connect to any existing
network. This is accepted.
7.52 The Council’s Environmental Specialist (Energy and Biodiversity) reviewed the
submitted details and raised no objection subject to a condition requiring a revised
Energy Strategy and a carbon offset contribution based on the updated Energy
Strategy and ‘be seen’ energy monitoring condition.
7.53 Subject to legal agreement and the recommended conditions, the proposal would
comply with Policies SI2 and SI3 of The London Plan, Policy EM1 of the Local
Plan Part 1, and Policies DMEI 2 and DMEI 3 of the Local Plan Part 2.
Waste Management
7.54 The Applicant submitted a Servicing and Waste Management Plan (Rev-P1.0,
prepared by Patrick Parsons, dated 06.07.2022).
The refuse storage is illustrated on proposed ground floor plans. The maximum
distances that refuse operatives should be require d to wheel containers,
measured from the furthest point within the storage/collection area to the loading
position at the back of the vehicle is 20 metres; this is achievable from the refuse
storage area. The Applicant proposes using a private waste collection company.
7.55 The Council’s Waste Services Team has reviewed the submitted documents and
raised no objection to the proposed development.
7.56 Subject to condition, the proposal would comply with Policy SI 7 of The London
Plan and DMHB 11 of the Local Plan Part 2.
Land Contamination
7.57 The Site is within a Potentially Contaminated Land area.
7.58 The Applicant submitted a Land Contamination Assessment (Desk Study and
Conceptual Site Model -V1.0, Reference: LS 0717, prepared by Land Science,
dated 25.03.2023). The Assessment’s conceptual site model identified
parameters for further intrusive ground investigations.
7.59 The Council’s Land Contamination Officer has been consulted and advised that
they have no objection to the proposed development. The Officer recommended
a land contamination condition which has been attached to this recommendation.
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
7.60 Subject to condition, the proposal complies with Policies DMEI 11 and DMEI 12
of the Local Plan Part 2.
Fire Safety
7.61 The Applicant submitted a Fire Statement (prepared by Fire Safety South East,
dated 11.07.2022), detailing the key fire safety features of the building.
7.62 The technical aspects of the materials to be used in any development, in relation
to fire safety, are considered under the Building Act (1984) and specifically the
Building Regulations, Approved Document B amended version (2022). These
require minimum standards for any development, although the standards would
vary between residential and commercial uses and in relation to new build and
change of use/conversions. The Regulations cover a range of areas including
structure and fire safety. Any person or organisation carrying out development can
appoint either the Council’s Building Control Service or a Registered Building
Control Approver to act as the Building Control Body (BCB), to ensure the
requirements of the Building Regulations are met. The BCB carry out an
examination of drawings for the proposed works and make site inspections during
construction work to ensure the works are carried out correctly. On completion of
work the BCB would issue a Completion Certificate to confirm that the works
comply with the requirement of the Building Regulations.
7.63 The fire strategy will be subject of further review during the detailed design stages
to ensure compliance with relevant building design codes of practice and
guidance.
7.64 The proposal complies with the aims of Policy D12 of The London Plan.
Archaeological Impact
7.65 The Site is within an Archaeological Priority Zone – Heathrow.
7.66 Accordingly, the Applicant submitted a Written Scheme of Investigation (reference
LP4196L-WSI-v1.2, prepared by LP Archaeology, dated July 2022).
7.67 The Local Planning Authority consulted Historic England’s Greater London
Archaeological Advisory Service (GL AAS), which reviewed the submission and
stated that ‘the development could cause harm to archaeological remains and field
evaluation is needed to determine appropriate mitigation. However, although the
NPPF envisages evaluation being undertaken prior to determination, in this case
consideration of the nature of the development, the archaeological interest and/or
practical constraints are such that I consider a two-stage archaeological condition
could provide an acceptable safeguard.’ GLASS concluded they had no objection
to the proposed development subject to condition and informative regarding a
Written Scheme of Investigation.
7.68 A Written Scheme of Investigation condition and informative is recommended.
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
7.69 Subject to condition, the proposal complies with the NPPF, Policy HC1 of The
London Plan, and Policy DMHB 7 of the Local Plan Part 2.
Heritage
7.70 Sipson House is Grade II Listed and is located 1.2km north of the site. Given the
significant distance between the two sites the proposal would have no impact
upon the setting of the designated heritage asset. As such the proposed
development accords with Policy DMHB 2 of the Local Plan Part 2.
Green Belt
7.71 The Site is not located within the Green Belt, however, the land to the north of the
Site, on the opposite side of Sipson Road, is designated Green Belt. The Site is
separated from the Green Belt land to the northeast by Sipson Road, and the
submitted documents demonstrate that the proposal would integrate with the
surrounding larger developments. Furthermore, the proposal would not have a
greater impact on the Green Belt than the previously approved scheme.
7.72 The proposal complies with Policy G2 of The London Plan, Policy EM2 of the
Local Plan Part 1, and Policy DMEI 4 of the Local Plan Part 2, and is supported.
Odour
7.73 The proposed hotel includes an ancillary kitchen. A planning condition is
recommended regarding extraction and odour control to protect amenity.
7.74 Subject to condition, the proposal complies with Policy D13 of the London Plan
and Policies DMHB 11 of the Local Plan Part 2.
Airport Safeguarding
7.75 The application site is located within the 3-kilometre Heathrow Airport
Safeguarding Zone . The height of development within these zones is restricted to
protect air traffic routes. The proposal is for a 7-storey building set within an area
of similar and taller height buildings. Heathrow Airport Safeguarding and the
National Air Traffic Services are statutory consultees for developments within
designated zones, both have been consulted and have raised no objection subject
to standard informative relating to the use of cranes to construct the development.
As such the proposal accords with Policy DMAV 1 of the Local Plan Part 2.
Planning Obligations
7.76 Policy DMCI 7 of the Local Plan Part 2 states to ensure development is
sustainable, planning permission will only be granted for development that clearly
demonstrates there will be sufficient infrastructure of all types to support it.
Infrastructure requirements will be predominantly addressed through the Council's
Community Infrastructure Levy (CIL). Planning obligations will be sought on a
scheme-by-scheme basis to secure the provision of affordable housing in relation
to residential development schemes, where development has infrastructure needs
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
that are not addressed through CIL, and to ensure that development proposals
provide or fund improvements to mitigate site -specific impacts made necessary
by the proposal. Applications that fail to secure an appropriate Planning Obligation
to make the proposal acceptable will be refused.
7.77 The Community Infrastructure Levy Regulation 2010 (Regulations issued
Pursuant to the 2008 Act) and the NPPF have put three tests on the use of
planning obligations into law. It is unlawful (since 6 April 2010) to request planning
obligations that do not meet the following tests:
i. necessary to make the development acceptable in planning terms
ii. directly related to the development, and
iii. fairly and reasonable related in scale and kind to the development
7.78 The effect of the Regulations is that the Council must apply the tests much more
strictly and can only request planning obligations that are genuinely necessary
and directly related to the development. Should the Council request planning
obligations that do not meet the policy tests, the Council would have acted
unlawfully and could be subject to a High Court challenge.
7.79 Section 106 Heads of Terms are as follows:
1. Air Quality Mitigation contribution of £974,383.
2. A Carbon Offset sum based on an Updated Energy Strategy to discharge
Condition 22, with the offset calculation based on £95 per tonne of CO2 over a
30-year period.
3. A Construction Employment Training Scheme secured in accordance with the
Council's Planning Obligations SPD.
4. An End-User Employment Scheme secured in accordance with the Council's
Planning Obligations SPD.
5. A Section 278 agreement to implement the proposed off-site Highways Works
and street tree planting on Sipson Road.
6. A Project Management and Monitoring Fee, equa lling 5% of the total financial
contributions to be paid under this agreement.
8 Other Matters
Human Rights
8.1 The development has been assessed against the provisions of the Human Rights
Act, and in particular Article 1 of the First Protocol and Article 8 of the Act itself.
This Act gives further effect to the rights included in the European Convention on
Human Rights. In arriving at this recommendation, due regard has been given to
the applicant's reasonable development rights and expectations which have been
balanced and weighed against the wider community interests, as expressed
through third party interests / the Development Plan and Central Government
Guidance.
Equality
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
8.2 Due consideration has been given to Section 149 of the Equality Act with regard
to the Public Sector Equality Duty in the assessment of this planning application.
No adverse equality impacts are considered to arise from the proposal.
Local Finance Considerations and CIL
8.3 As of 1 April 2012, all planning approvals for schemes with a net additional internal
floor area of 100 sq. m. or more were liable for the Mayoral Community
Infrastructure Levy (CIL), as legislated by the CIL Regulations 2010 and The CIL
(Amendment) Regulations 2011. From April 2019, the liab ility payable is £60 per
sq. m. The MCIL2 charging schedule rate, including indexation for calendar year
2025, is £71.09 per sq. m.
8.4 The London Borough of Hilli ngdon Council is a collecting authority for the Mayor
of London, and this liability shall be paid to the London Borough of Hillingdon
Council in the first instance.
8.5 In addition to MCIL2, the development represents Chargeable Development
under the Hillin gdon CIL, which came into effect on 1 August 2014. The liability
payable is as follows:
Hotels – £40 per sq. m.
8.6 This CIL liability is in addition to the Section 106 planning obligations.
8.7 The proposed development consists of the following floor areas:
8.8 Hotel (Use Class C1) – 5,619 sq. m.
8.9
8.10
The construction of these floor areas results in the following CIL charges:
Local CIL – £370,806.58
Mayoral CIL – £399,459.82
Please note this has been calculated based on the information available to the
officer. The final amount will be reviewed post -determination by the Council's
Planning Obligations Team and set out to the liable party in line with the CIL
Regulations.
9 Conclusion / Planning Balance
9.1 The principle of redeveloping the Site for a Hotel is supported in this instance. The
building’s height, scale, and mass are compatible with the height and scale of
surrounding development. The development would not have any detrimental
impact on the street scene, upon residential amenity, or upon the setting of the
Green Belt land opposite the Site. The Local Planning Authority has worked with
the Applicant to refine the development’s design during the full planning
application process, securing additional planting and a reduction in hardstanding
to the front of the Site to improve the street and public realm. There are no
Hillingdon Planning Committee – 4th September 2025
PART 1 – Members, Public & Press
objections from the Council’s Urban Design Officer, Landscape Officer, or
Highways Officers. While located on Potentially Contaminated Land, the Council’s
Land Contamination Officer has no concerns subject to the recommended
condition. Similarly, whilst within an Archaeological Priority Zone, Historic
England’s Greater London Archaeological Advisory Service (GL AAS) has no
objection subject to the attached conditions. Noting the Air Quality Management
Area (AQMA) and Air Quality Focus Area, which the Site is within, the Council’s
Air Quality Officer has no objections subject to an air quality mitigation contribution
of £974,383 (contained within the Section 106 Heads of Terms) and planning
conditions, which have been recommended.
9.2 The proposal is acceptable and would be consistent with the National Planning
Policy Framework, The London Plan, and Hillin gdon Local Plan.
9.3 The planning application is therefore recommended for approval subject to the
conditions set out in Appendix 1 and Section 106 Heads of Terms detailed on the
previous page.
10 Background Papers
10.1 Relevant published policies and documents taken into account in respect of this
application are set out in the report. Documents associated with the application
(except exempt or confidential information) are available on the Council's
website here, by entering the planning application number at the top of this
report and using the search fac ility. Planning applications are also available to
inspect electronically at the Civic Centre, High Street, Uxbridge, UB8 1UW upon
appointment, by contacting Planning Services at planning@h illingdon.gov.uk.
AAPPENDICES
Planning Application
829/APP/2023/312
Hillingdon Planning Committee -
PART 1 - MEMBERS, PUBLIC & PRESS 1 of 28
AAppendix 1: Recommended Conditions and Informatives
Conditions
1. COM3 T Time Limit
The development hereby permitted shall be begun before the expiration of three years from
the date of this permission.
REASON
To comply with Section 91 of the Town and Country Planning Act 1990.
2. COM4 A Accordance with Approved Plans
The development hereby permitted shall not be carried out except in complete accordance
with the details shown on the submitted plans:
19040-GAA-ZZ-00-DR-T-0101 (Location and Block Plan)
19040-GAA-ZZ-B1-DR-T-2001 (Proposed Basement GA Plan)
19040-GAA-ZZ-00-DR-T-2002-Rev-P06.06 (Proposed Ground Floor Plan)
19040-GAA-ZZ-00-DR-T-2002-Rev-P06.05 (Revised Proposed Ground Floor GA Plan)
19040-GAA-ZZ-01-DR-T-2003 (Proposed First Floor GA Plan)
19040-GAA-ZZ-02-DR-T-2004 (Proposed Second Floor GA Plan)
19040-GAA-ZZ-03-DR-T-2005 (Proposed Third Floor GA Plan)
19040-GAA-ZZ-04-DR-T-2006 (Proposed Fourth Floor GA Plan)
19040-GAA-ZZ-05-DR-T-2007 (Proposed Fifth Floor GA Plan)
19040-GAA-ZZ-06-DR-T-2008 (Proposed Sixth Floor GA Plan)
19040-GAA-ZZ-07-DR-T-2009 (Proposed Roof Access GA Plan)
19040-GAA-ZZ-RF-DR-T-2010 (Proposed Roof Plan)
10513-LA-01-Rev-P1 (Proposed Biodiverse Green Roof Plan)
10513-LA-02-Rev-X (Proposed Landscape Plan)
19040-GAA-ZZ-XX-DR-T-2101 (Proposed Front/North Elevation)
19040-GAA-ZZ-XX-DR-T-2102 (Proposed Rear/South Elevation)
19040-GAA-ZZ-XX-DR-T-2103 (Proposed Side/East Elevation)
19040-GAA-ZZ-XX-DR-T-2104 (Proposed Side/West Elevation)
19040-GAA-ZZ-XX-DR-T-2201 (Proposed Section A-A)
19040-GAA-ZZ-XX-DR-T-2500-Rev-P01.1 (Proposed Front Facade Details)
19040-GAA-ZZ-XX-DR-T-2500-Rev-P01.1 (Proposed Front Facade Section Details)
19040-GAA-ZZ-XX-DR-T-2501-Rev-P01 (Proposed Front Facade Details)
19040-GAA-ZZ-XX-DR-T-2500-Rev-P01 (Proposed Front Facade Section Details)
CGV-1103-02-Rev-P2 (Swept Paths)
SPS-PPC-00-XX-DR-C-001 (Swept Path Analysis)
CGV-1103-101-Rev-P1 (Proposed Access)
and shall thereafter be retained/maintained for as long as the development remains in
Hillingdon Planning Committee -
PART 1 - MEMBERS, PUBLIC & PRESS 2 of 28
existence.
REASON
To ensure the development complies with the provisions of The London Plan (2021) and the
Local Plan Parts 1 (2012) and 2 (2020).
3
3. COM5 G General compliance with supporting documentation
The development hereby permitted shall not be carried out except in complete accordance
with the details shown on the submitted documents, references:
- Preliminary Basement Impact Assessment-Rev-0, reference SRW-PPC-00-XX-RP-G-0012,
prepared by Patrick Parsons, dated 19.05.2023 _ received 04.10.24
- BREEAM Pre-Assessment Report, Reference 21-8895, prepared by Syntegra, dated
03.08.2022 _ received 04.10.24
- Desk Study and Conceptual Site Model-V1.0, Reference: LS 0717, prepared by Land
Science, dated 25.03.2023 _Part 1 of 3 _ received 04.10.24
- Drainage Strategy-Rev-P03, reference 18403-RLL-22-XX-RP-C-001, prepared by RLRE
Consulting Engineers, dated 30.06.2022
- Air Quality Assessment, reference, AQ2114, prepared by GEM Air Quality Ltd, dated July
2022
- Arboricultural Impact Assessment, reference HWA10759-APIII, prepared by Hallwood
Associates, dated 20.06.2022
- Bird Hazard Management Report, prepared Henriette Westergaard, dated June 2022
- Design and Access Statement-Rev-P01, prepared by GAA, dated 18.07.2023
- Fire Statement, prepared by Fire Safety South East, dated 11.07.2022
- Noise Impact Assessment, reference 23907.NIA.01, prepared by KP Acoustics, dated
13.07.2022
- Planning Statement, reference JCC6291, prepared by Cunnane Town Planning, dated
August 2022
- Preliminary Ecological Appraisal, prepared by Henriette Westergaard, dated 04.07.2022
- Sequential Assessment Scoping Note, prepared by Turley
- Sequential Assessment, reference GAAP3000, prepared by Turley, dated November 2023
- Servicing and Waste Management Plan-Rev-P1.0, prepared by Patrick Parsons, dated
06.07.2022
- Transport Statement-Rev-1.0, prepared by Patrick Parsons, dated 30.06.2022
- Travel Plan-Rev-1.0, prepared by Patrick Parsons, dated 06.07.2022
- Written Scheme of Investigation, reference LP4196L-WSI-v1.2, prepared by LP
Archaeology, dated July 2022
Thereafter the development shall be retained/maintained in accordance with these details for
as long as the development remains in existence.
REASON
To ensure that the development complies with the objectives of The London Plan (2021) and
the Local Plan Parts 1 (2012) and 2 (2020).
Hillingdon Planning Committee -
PART 1 - MEMBERS, PUBLIC & PRESS 3 of 28
44. NONSC N Non Standard Condition
The development hereby approved is for a hotel with 108 bedrooms. This is the maximum
number of bedrooms permitted by this consent and any subdivision or creation of new
bedrooms above this number would require separate planning consent.
REASON
To ensure the hotel is used as proposed in accordance with Policies E10 and D6 of The
London Plan (2021) and Policies DME 5 and DMHB 16 of the Local Plan Part 2 (2020).
5. COM7 M Materials (Submission)
Notwithstanding the approved drawings, prior to the commencement of any works on the
facade or the supporting structure/substructure, details of all materials and external surfaces
shall be submitted to and approved in writing by the Local Planning Authority. Details shall
include information relating to make, product/type, colour, and photographs/images.
Thereafter the development shall be constructed in accordance with the approved details
and be retained as such.
REASON
To ensure that the development presents a satisfactory appearance in accordance with
Policy DMHB 11 of the Hillingdon Local Plan Part 2 (2020).
6. NONSC C Construction Management Plan
Prior to the commencement of development (including demolition, site clearance, and initial
ground investigation works), a Construction Management Plan shall be submitted to, and
approved in writing by the Local Planning Authority in consultation with Transport for
London. The plan shall detail:
(i) The phasing of development works.
(ii) The hours during which development works will occur.
(iii) A programme to demonstrate that the most valuable or potentially contaminating
materials and fittings can be removed safely and intact for later re-use or processing.
(iv) Measures to prevent mud and dirt tracking onto footways and adjoining roads (including
wheel washing facilities).
(v) Traffic management and access arrangements (vehicular and pedestrian) and parking
provisions for contractors during the development process (including measures to reduce
the numbers of construction vehicles accessing the site during peak hours).
(vi) Measures to reduce the impact of the development on local air quality and dust through
minimising emissions throughout the demolition and construction process.
(vii) The storage of demolition/construction materials on site.
(ix) Measures to demonstrate compliance with the GLA's Control of Dust and Emissions
from Construction and Demolition SPG.
(x) All Non-Road Mobile Machinery (NRMM) of net power of 37kW and up to and including
560kW used during the demolition, site preparation and construction phases shall comply
Hillingdon Planning Committee -
PART 1 - MEMBERS, PUBLIC & PRESS 4 of 28
with the emission standards set out in https://www.london.gov.uk/programmes-and-
strategies/environment-and-climate-change/pollution-and-air-quality/nrmm. Unless it
complies with these standards, no NRMM shall be on site, at any time, whether in use or
not, without the prior written consent of the local planning authority. The developer shall
keep an up-to-date list of all NRMM used during the demolition, site preparation and
construction phases of the development on the online register at https://nrmm.london/.
(xi) Details of cranes and other tall construction equipment (including the details of obstacle
lighting) in consultation with the Ministry of Defence (MoD).
The approved details shall be implemented and maintained throughout the demolition and
construction process.
REASON
To reduce the impact on air quality during construction, protect amenity, and ensure
highways safety and to ensure that construction work and construction equipment on the site
and adjoining land does not obstruct air traffic movements or otherwise impede the effective
operation of air traffic navigation transmitter/receiver systems in compliance with Policies T7,
GG3, and SI 1 of The London Plan (2021), The GLA's Control of Dust and Emissions during
Construction and Demolition SPG, and Policy DMAV 1 of the Local Plan Part 2 (2020).
7
7. NONSC C Construction Logistics Plan (CLP)
Prior to the commencement of development (including demolition, site clearance, and initial
ground investigation works) a Detailed Construction Logistics Plan (CLP) shall be submitted
to and approved by the