FROM HS2
Clarification on 2 sets of Roadworks that have been recently advertised by LBH Highways
There have been lots of residents contacting LBH via email & social media about the 2 sets of works below that they would like to provide clarification on:
HS2 Road Closure of Breakspear Road South conflicting with Cadent Gas Road Closure of Ickenham Road/Ruislip High Street Junction – Feb 2026
Road Closure of Breakspear Road South (Service Road) for Affinity Water Main Replacement – March to July 2026
New Future Works Breakspear Road South – 24/7 Road Closure over 5 Days – Sat 14/02 at 7am until Wed 18/02 at 7pm
HS2/SCS have agreed a Road Closure of Breakspear Road South that will take place 24 Hours a Day over a 5 Day Period from Sat 14/02 at 7am until Wed 18/02 at 7pm.
These works have been scheduled to take place during the Feb 2026 School Half-Term to cause as little disruption as possible but we are aware there is never a good time to close this road.
Previously LBH had been informed by HS2 that all Road Closures on Breakspear Road South would be completed in 2025 but the following works are now required and unfortunately due to the methodology of the works they will require Full Road Closures to complete them:
Please note – once the Trial Hole data is received, HS2/SCS will need to complete the Sewer Connection which will require a further Road Closure that they would look to request for the May School Half-Term or the School Summer Holidays.
The Diversion Route is via Breakspear Road, Bury Street (A4180), Ickenham Road (B466), High Road, Swakeleys Road (B467).
There will be no access via Breakspear Road South during the Road Closure for Emergency Service Vehicles.